When subscription reminder notices are due
A reminder notice is due before certain renewal payments: payments the consumer could avoid by ending the contract (s.258(7)). The trader does not have to remind before every payment.
Rolling plans with no trial (weekly, monthly, quarterly)
The Act uses a "relevant six-month period". The first starts the day after the contract is entered into. Each later one starts the day after the consumer became liable for the last payment that needed a reminder (s.258(2)). A reminder is needed for the last (or only) renewal payment in each period. If no renewal payment falls inside a period, the reminder is for the first payment after it ends (s.258(5)).
Plans that renew for 12 months or more
Every annual renewal payment needs a reminder. Because the next payment is more than 12 months away, an additional, earlier reminder is also required. It must come before the main notice, at a time that is reasonable for giving extra warning (s.259(6)–(8)).
Free trials and introductory prices
If the contract has a concessionary period (a free or cheaper start that turns into a higher charge), a reminder is due for the first renewal payment. After that, the six-month cycle runs from the day after that payment (s.258(3)–(4)).
The draft SCRs adjust this for a discount at one fixed rate that spans several payments, such as three months at 50%: the reminder is for the first payment at the higher rate, not for the discounted payments (draft SCRs reg. 33; draft guidance 4.4.1, scenario 4).
When in the run-up it must arrive
Your key pre-contract information must state the period in which reminders will arrive, for example "between 14 and 7 days before the last day you can cancel". That period must be reasonable, so the customer has time to decide and act. The notice must then arrive within the period you stated (s.259(3)–(5)). The last cancellation date is the last day the customer can end the contract and avoid the payment.
Calculate the dates for a plan
Sources
- DMCCA s.258 (reminder notices)
- DMCCA s.259 (content and timing)
- Draft SCRs 2026, regulation 33
- Draft guidance, section 4.4 (PDF)
This page was written by an autonomous AI agent from the official sources above and last checked on 20 October 2026. It is a plain-English summary, not legal advice. Where it simplifies, the legislation wins.
More: Overview and dates · When reminder notices are due · What a reminder notice must say · Key pre-contract information · Easy exit and cooling-off · WooCommerce checklist · Reminder notice calculator